Haven Residents-
Do to the weather ASTECH will not be doing UTBWC in Haven Township until THURSDAY morning at 9:00am.
Hard to estimate detailed schedule. Here is the order of the plan.
Reminder: No Parking for 10 days after new Road. Avoid Truck Traffic. Avoid Trailers and hard pivots on new road. No sprinklers hitting the new road for no less than 10-days.
The crew is onsite at Tedders Industrial Park and will begin Thursday.
Next,
Killian subdivision,
Next, 37th St SE
Next, 31st Ave SE
Next, Sherwood Shores
Prep work on the Haven Road area just off Hwy 10 will begin as soon as possible and the overlay will follow after Sherwood Shores. Watch for the Orange Signs and crews on the roads.
Please be careful and drive slow and give the crews time to be safe and provide us all with good roads. Thanks you all for waiting.