Road Construction Notice to Residents Haven Township

2025 Road work will begin in Haven Township May 12th, 2025.   

Astech is our contracted company and will begin work in order listed below.

1. DeerHaven Subdivision- Week of May 12th- starting out

2. Tedders Industrial Park- 

3. Killian Subdivision

4. 31st Ave SE

5. Sherwood Shores 

6. Haven Road area on the Frontage road off Hwy 10.  Possible 1st week of June.

Schedule is to be finished close to end of May 2025.   You will see warning signs and yard signs for NO Parking . Please not to have any sprinkler working that will spray on the road surface.    Vehciles could be tagged and towed away if the crew determines the vehicle stops the work.

No Truck traffic will be permitted on the new surface for 10 days to get the new road time to set-up cure.   Asking you also avoid use of tandem on trailers ( dual axles )  from turning and doing harm to new road.  If you see somehting report it and get us a license number for enforcing the road restriction.  

Questions please contact us.

Joe Then  320-406-1436

Eric Meyer 320-406-1720